BADARPUR THERMAL POWER STATION
#1

BADARPUR THERMAL POWER STATION
[attachment=17860]

INTRODUCTION

BTPS was conceived in 1965 to meet the growing electricity demand of Northern Region.

The site construction activities started in 1968.

The plant became operational with the commissioning of its first unit on 26th July 1973, 2nd unit in ;74 , 3rd unit in 75 , 4th unit in 78 & 5th unit in 81.

Maintenance Management System
Objective: Maximizing Availability Through:
Identifying maintenance needs and applying appropriate maintenance methods and their implementation in time bound manner.

It involves:
Long Tem Planning
Short Term Planning
System Planning
Predictive Maintenance
Breakdown maintenance reduction
Renovation and Modernization

ENVIRONMENT MANAGEMENT

RECEIVED GOLDEN PEACOCK AWARD 2003 FOR ENVIRONMENT PROTECTION AT PALAMPUR,HP.

RECEIVED INDO-GERMAN GREENTECH EXCELLENCE
AWARD FOR ENVIRONMENT PROTECTION FOR THE
YEARS 2001 & 2002.

RECEIVED CORP. ENVT. AWARD OF NTPC FOR 2000- 2001.

APPRECIATION CERTIFICATE FROM CHIEF MINISTER, DELHI TO THE TEAM OF BTPS FOR PARTICIPATION IN YAMUNA CLEANING ABHIYAN.

HR Initiatives contd.

Training enphasis for all employees atleast 7 days in a year , Up-gradation of technical knowledge and skill through retraining and monitoring of learning index.

Responsibility accounting & Subordinate development.

Inspiring people to become leaders at all levels.

Implementation of the concept of HR Ambassadors .